New Delhi: Denizens of Kanpur are wanting ahead to their New Yr present as Prime Minister Narendra Modi on Tuesday will inaugurate the finished part of the Kanpur Metro Rail Undertaking at round 1.30 pm.

The event within the metro line comes after the profitable run of Metro in three cities Lucknow, Ghaziabad, Noida, and Larger Noida within the state. Kanpur will turn into the fourth metropolis to get the metro.

ALSO READ: ‘Raining Injustice’: Rahul Gandhi Hits Out At Centre For Police Motion On Docs Throughout Protest

PM Modi may also examine the Metro Rail Undertaking and undertake a metro experience from the IIT metro station to Geeta Nagar.

Attention-grabbing information in regards to the Kanpur Metro Rail Undertaking

The 9 km lengthy part of the Kanpur Metro Rail Undertaking stretches from IIT Kanpur to Moti Jheel.

The size of the Kanpur Metro Rail Undertaking is 32 km and the estimated price of the venture is Rs11,076.48 crore.

The development work was began on November 15, 2019, and the trial run occurred on the 9 km IIT to Motijheel Precedence Hall on November 10, 2021.

On completion of the metro venture, about 40 lakh passengers will profit. The state goals to run Metro in most 9 cities.

IIT Kanpur to Naubasta hall will go by way of the guts of town masking a number of distinguished academic establishments, Railway & Bus Stations, together with IIT Kanpur. CSJM College. GSYM Medical School, Jhakarkati Bus Station and Kanpur Central Railway Station, and so on.

Right here’s the timeline of the venture

  • October 4, 2016 – Akhilesh authorities laid the inspiration stone of Kanpur Metro
  • 20 September 2017 – The Centre requested to make an in depth venture report (DPR) once more
  • 5 September 2018 – UP authorities despatched new DPR of Kanpur Metro to the Centre
  • 28 February 2019 – The Union Cupboard authorized the Kanpur Metro
  • 8 March 2019 – PM Modi laid the inspiration stone of Kanpur Metro
  • 15 November 2019 – CM Yogi inaugurated the development work of Kanpur Metro
  • 10 November 2021 – Kanpur Metro’s official trial run begins

Right here’s the map of the route inaugurated at present

The metro will begin from IIT Kanpur to go by way of Kalyanpur, SPM Hospital, College, Gurudev Sq., Geetanagar, Rawatpur, LLRH, Motijheel.

Examine Route 1 particulars right here

The 23.8 km lengthy will start from IIT and go until Naubasta. There are complete 22 stations which embody 14 above-ground stations and eight stations underground.

Route 2 particulars

It is going to be 8.60 km lengthy masking Agriculture College to Barra-8.  There will likely be complete of eight stations. There will likely be 4 stations above floor and 4 stations underground.

 

[ad_2]